| LEE provided services for the design, manufacture and
construction of a water reclamation plant utilizing advanced treatment technology.
An Electro Dialysis Reversal (EDR) was used to reclaim70 gallon per minute (GPM) from 87
GPM of wastewater from the plating operation. The plant was designed and constructed
to allow for future expansion to reclaim up to 240 GPM of water. The project won an
award from the City of San Jose, recognizing FMC for their part in water conservation. All systems were manufactured based on Underwriter Laboratory (UL) standards
and all systems bear a UL stamp.
During the construction of the treatment pad, contaminated
soil was excavated. From LEE's exhibited capability of handling such obstacles, LEE
was contracted to excavate the contaminated soil and haul it off site while staying within
the schedule.
LEE also obtained the necessary Hazmat permits and those
required by the fire and building departments. |